Continuing its plan to meet future requirements, the client initiated an upgrade of Bimha Mine, aiming to achieve a capacity of 3.1 million tonnes per year. This north section phase of the project involved surface conveyors, underground crushing facilities, strike and decline conveyors, as well as five pipelines. Work commenced in late 2022 and continued through early 2023.
The fabrication and delivery of galvanized steelwork were managed by our partners, Viva Engineering, in South Africa.
Painted platework was fabricated in Hogarths’ Bulawayo workshop.
Hogarths also handled the installation of steelwork, platework, free-issue mechanicals, and piping.